Peter Pollack papers   1965-2009  (bulk 1980-2005 )
full text File Size: 209 K bytes | Add this to my bookbag

   Container / Location    Title
 
Pfizer Campus Projects [series]:

The Pfizer Campus Projects (4.5 linear feet, 22 tubes, 5 oversize folders) subseries includes correspondence, minutes, permit applications, study results, plans, drawings, and sketches related to the Warner-Lambert, Parke-Davis, and Pfizer in Ann Arbor. There is a small amount of material related to the Kalamazoo campus as well. Major projects profiled include the Parke-Davis master plan, the 2800 Plymouth Road Facility, Pfizer's Planned Unit Development (PUD), and Stormwater Wetlands Management.

 
Textual Files
 
Parke-Davis/Warner Lambert
 
Master Plan
Box   17  
Relocation Master Plan,  1984
Box   17  
Master Plan,  1984
Box   17  
Master Plan,  1985
Box   17  
Master Plan,  1989-1990
Box   17  
Master Plan Update,  1996
 
Master Plan with Heidi
Box   17  
Master Plan,  1996-1997
Box   17  
Background Materials
Box   17  
Correspondence File,  1996 (2 folders)
Box   17  
Master Plan III,  2000
Box   17  
Building 20 Addition,  1998
Box   17  
Documentation,  1997
Box   17  
Graphics
Box   17  
Working Session,  1998
Box   17  
Master Site Plan/Strategic 7 Year Plan,  1997
Box   17  
Master Plan Report,  1997 (2 folders)
 
2800 Plymouth Road Facility
Box   17  
Alternate
Box   17  
Building 26 Pre-Clinical Laboratory,  1999
Box   17  
Building 26 Site Plan,  2000
Box   17  
Cafeteria Conference Center Plan,  1998
Box   17  
Childcare Center,  1998
Box   17  
FAR Calculations,  1999
Box   17  
Landscape Maintenance Proposal Form draft,  1990
Box   17  
Materials Handling Center and Conference Cafeteria Center,  1998
Box   17  
Materials Handling Center Plan,  1998
Box   17  
Materials Handling Center Specs,  1998
Box   17  
Power House Addition,  1993
Box   17  
Power House Addition/South Parking Lot Site Plan,  1993
Box   17  
Project Management and Communication,  1999
Box   17  
Site Plan,  1998
 
2800 Plymouth Road Facility
 
South 15 Acres
Box   17  
New Site Development,  1993
 
Project Book
Box   17  
Construction Meetings,  1993-1995
Box   17  
Submittals,  1993-1994
Box   17  
Addendum,  1993-1994
Box   17  
Pay Estimates,  1993-1994
Box   17  
Miscellaneous,  1993-1994
 
Technical Development Facility
Box   18  
General,  1998
Box   18  
Submittal Originals,  1996-1999
Box   18  
Site Plan,  1998-2005 (2 folders)
Box   18  
Site Work -- Issued for Construction,  1998
Box   18  
Preliminary Detention Study,  November 1, 1990
Box   18  
Re-Zoning Application,  September 14, 1992
Box   18  
Traffic Study,  1990
 
Pfizer
 
Master Plan/Planned Unit Development (PUD)
Box   18  
Ann Arbor Planning Department Reports,  1992-2001
Box   18  
Baxter Road Entrance and Guard Kiosk Plans,  2005
Box   18  
Building 10 Executive Courtyard,  2003
Box   18  
Building 28 Plans,  2006
Box   18  
Building 35 Plans,  2005
Box   18  
Buildings 85 and 75,  2003
Box   18  
Campus Enhancements III,  2005
 
Chronological File
Box   18  
 January-October, 2001
Box   18  
 September-October, 2001
Box   18  
 November-December, 2001
Box   18  
 January-February, 2002
Box   18  
 August-October, 2002
Box   18  
 November-December, 2002
Box   18  
 January 2003
Box   18  
cGMP Warehouse Plans,  2006
Box   18  
Community Context and Redevelopment Opportunities,  2007
Box   18  
Concept Master Plan sketches,  2001
Box   18  
Engineering,  2000
Box   18  
Global Facilities Management Information Document,  2002
Box   18  
Guard Kiosk and Site Improvements,  2004
Box   18  
Informational,  2000-2002
Box   18  
Land and Water Management -- Wetland Inventory,  2000
Box   18  
Lawn Conversion -- Phase IV,  2005
Box   18  
Lighting,  2000
Box   18  
Master Plan Edits,  2003
Box   18  
Master Planning,  2001-2003 (3 folders)
Box   19  
Master Plan Meetings,  2001-2003
Box   19  
Master Plan Overlays,  2002
Box   19  
Master Plan Proposals,  2000-2002
 
Natural Features
Box   19  
55 Acre Site Natural Features Inventory,  2001
Box   19  
Landmark Tree Survey,  2001
Box   19  
Natural Features,  2002
Box   19  
Natural Features Data,  2002
Box   19  
Natural Features Inventory,  2002
Box   19  
Veridian Botanical Inventory and Landmark Tree Survey,  2002
Box   19  
Parking,  2008
Box   19  
Patrick Judd File,  2001-2002
Box   19  
Plans and Graphics,  2002
Box   19  
Prairie Conversion -- Phase II,  2003
Box   19  
Project Review Coordination,  1999
Box   19  
Sanitary Sewer Analysis,  2001
Box   19  
Scanned Photos,  undated
Box   19  
Site Design Standards,  2002
Box   19  
Site Options Study,  2001
Box   19  
Site Photographs
Box   19  
Site Planning and Design Team Meeting,  2004
Box   19  
Site Plans for Parking Structure and Wetlands Use Permit,  2000
Box   19  
Strategic Facilities Plan,  2004
Box   19  
Strategic Site Plan and Master Plan Review,  2003
Box   19  
Strategic Site Plans,  2000-2005 (5 folders)
 
Zoning
Box   19  
Rezoning and Area Plan,  2002
Box   19  
Zoning,  2001-2002
Box   19  
Zoning Petition,  2001
Box   19  
Coordination Meeting,  2003
Box   19  
Coordination Meeting Minutes,  1998-2002 (3 folders)
Box   20  
Coordination Meeting Minutes,  1998-2002 (2 folders)
 
Miller's Creek
Box   20  
Breakfast and Open House,  2003
Box   20  
Correspondence,  2001-2003 (2 folders)
Box   20  
Crossing Options,  2004
Box   20  
Grant Application,  2005-2006
Box   20  
Watershed Improvement Plan,  2003
Box   20  
Site Acquisition,  2001
 
Stormwater Wetlands Management
Box   20  
Building 14 Courtyard,  2000
Box   20  
Detention Basin 3,  2001-2002
 
Land and Water Management Master Plan
Box   20  
DEQ Permit Correspondence,  2000
Box   20  
Site Improvement,  2000
Box   20  
Specifications,  2000
Box   20  
Photographs
 
Stormwater Management Master Plan
Box   20  
Bid Period,  2000
Box   20  
Calculations,  2000
 
Chronological File
Box   20  
 September-December, 1999
Box   20  
 January-May, 2000
Box   20  
 June-July, 2000
Box   20  
 March 2001
Box   20  
Storm Water Management Study,  2001
Box   20  
Stormwater Research Introduction,  2002
Box   20  
Stormwater Update,  1984-1999
Box   21  
Wetland Annual Monitoring Report,  2003
Box   21  
Wetland Investigation and Delineation,  2001
Box   21  
Wetland Monitoring -- Basin 3,  2001-2002
Box   21  
Wetland Use Permit,  2000
 
Drawings and Plans
 
Parke-Davis/Warner-Lambert
Drawer   2 Folder 8  
Building 10 Courtyard-Preliminary Planting Plan,  August 14, 1992
 
Child Care Center
Drawer   2 Folder 8  
Miscellaneous sketches,  1998
Drawer   2 Folder 8  
Playground Concept Sketch,  March 31, 1999
 
The Courtyard
Drawer   2 Folder 8  
Existing Conditions,  January 26, 1987
Drawer   2 Folder 8  
Sketch Options,  January 1987
Drawer   2 Folder 8  
Courtyard Planting Plan,  March 4, 1987
Drawer   2 Folder 8  
Miscellaneous sketches
 
Entry Gate and Signage
Drawer   2 Folder 9  
Miscellaneous Plans and Drawings,  1992
Drawer   2 Folder 9  
Signage sketches,  undated
Drawer   2 Folder 9  
Master Plans Studies,  1992-1993
 
North Entrance Court
Drawer   2 Folder 9  
Miscellaneous sketches
Drawer   2 Folder 10  
Parking Deck-Miscellaneous sketches and plans
Drawer   2 Folder 10  
Switch Box Buffer-Concept Sketches,  June 21, 1999
Drawer   2 Folder 10  
Toxicology Building-Planting Plans,  May 8, 1985
Drawer   2 Folder 10  
Miscellaneous Plans
Tube   17  
Administration Support Facility Plans,  September 8, 2000
 
Building 26
Tube   17  
Building 23 & 26 Phase II Construction Drawings,  June 9, 2000
Tube   17  
Building 26 Phase II Construction Drawings,  August 1, 2000
Tube   18  
Building 26, Pre-Clinical Laboratory, and Parking Site Improvement Plans,  December 4, 2002
Tube   18  
Miscellaneous Sketches
Tube   18  
Building 35 Addition,  September 2, 2004
Tube   18  
Building PC-1 Preliminary Planting Plan Options,  undated
Tube   19  
Child Care Center-Plans Issued for Bidding,  June 1, 1999
 
Clinical Research Building 16
Tube   19  
General Trades,  September 4, 1990
Tube   20  
Site and Foundation Package,  April 19, 1990
Tube   20  
Cooling Towers -- Issued for Construction,  June 2, 1997
 
Entry Gate and Signage
Tube   21  
Miscellaneous Plans and Drawings,  1992
Tube   21  
Signage sketches,  undated
 
Fitness Trail
Tube   21  
Seed Mix Layout Modifications,  May 1989
Tube   21  
Preliminary Parcour Layout,  August 1988
Tube   21  
Fitness Trail Layout Record,  November 2, 1988
Tube   21  
Future Development Plan Options,  undated
 
Granite Sculpture Site Improvements
Tube   21  
Issued for Owner's Review,  April 16, 2002
Tube   21  
Issued for Construction,  August 12, 2002
Tube   22  
Huron Parkway Connector Tunnel -- Construction Issue, Site Work,  December 14, 2000
 
Land and Water Management
Tube   22  
Plans Issued for Construction,  May 17, 2000
Tube   22  
Re-Application for Inland Lakes and Stream Permit,  May 12, 2000
Tube   23  
Master Plans Studies,  1992-1993
Tube   23  
Materials Handling Center and Cafeteria Conference Center Site Improvement Plans,  March 22, 1999
 
New Site Development: South 15 Acres
Tube   23  
Plans Issued for Construction,  September 8, 1993
 
North Entrance Court
Tube   23  
Conclusion of Design Development Plans,  March 9, 2001
Tube   24  
Miscellaneous Plans,  2001
Tube   24  
Program/Character Discussion Diagrams,  October 2000
Tube   24  
North Parking Addition,  July 11, 1997
Tube   24  
North Parking Lot Area and Southwest Trucking Dock,  July 11, 1989
 
Parking Deck
Tube   25  
Phase II Minor Modification,  February 1990
Tube   25  
Issued for Construction,  November 29, 1990
Tube   25  
Parking Lots B, C, and D Relocation and Minor Building Additions,  July 19, 1999
Tube   26  
Power House Addition, South Parking Lot, and Entry Drive
Tube   26  
Appendix A,  June 2, 1993
Tube   26  
Wetland Permit Application,  May 27, 1993
Tube   26  
Administrative Amendment,  April 4, 1994
Tube   26  
As-Built Record,  March 7, 1995
Tube   26  
Preliminary Sketch Landscape Plan,  April 29, 1993
Tube   27  
Southern Parking Area Earthwork and Reforestation,  February 26, 1990
Tube   27  
Southwest Entry Schematic Designs,  June 9, 2004
Tube   27  
Storm Sewer Tie-In Plans,  1991
Tube   27  
Storm Water Management Master Plan,  2000
 
Switch Box Buffer
Tube   27  
Plans Issued for Bidding,  August 1, 1999
Tube   28  
Technical Development Facility
Tube   28  
Plans Issued for Construction,  August 3, 1999
Tube   28  
Administrative Amendment,  October 18, 2005
Tube   28  
Site Capacity Diagram
Tube   28  
Temporary Modular Addition to Building 50,  December 17, 1998
Tube   29  
Temporary Modular Office Addition
Tube   29  
Plans Issued for Bidding,  April 13, 1998
Tube   29  
Plan Submitted for Administrative Amendment,  April 1, 1998
Tube   29  
Temporary Parking Relocation -- Issued for Construction,  May 9, 2000
 
Toxicology Building
Tube   29  
Proposed Planting Plans,  April 1985
Tube   29  
Planting Plans,  May 8, 1985
Tube   29  
Tree Area Removal and Relocation Proposals,  April 1990
 
The Pond and Building Edge
Tube   30  
Preliminary Sketch Options,  January 1987
Tube   30  
Final Preliminary Plan,  February 10, 1987
Tube   30  
Planting Plan,  March 4, 1987
 
University of Michigan
Tube   30  
Preliminary Grading Plan,  November 1990
Tube   30  
Tree Relocation,  November 1990
Tube   30  
Regrading and Soil Stabilization Plan,  July 1992
Tube   30  
Miscellaneous Plans and Drawings
 
Pfizer
Drawer   2 Folder 11  
 1600 Site Plan Schematics,  April 2006
Drawer   2 Folder 11  
Building 10Executive Courtyard Sketches,  2003
Drawer   2 Folder 11  
Building 28 Loading Dock Renovation and South End Distribution -- Sketches,  2006
Drawer   2 Folder 11  
Campus Green and Entrance Plaza,  July 2000
Drawer   2 Folder 11  
Development Office Building Site Influences,  November 26, 2003
Drawer   2 Folder 11  
ERIN Walks and Planting Schematic,  February 18, 1993
 
Kalamazoo Campus
Drawer   2 Folder 11  
Final Schematic Options,  September 2008
Drawer   2 Folder 11  
Lot 1 Options,  August 2008
Drawer   2 Folder 11  
Rough Grading Options,  December 2005
Drawer   2 Folder 12  
Sketches
Drawer   2 Folder 12  
Studies,  2000
 
Miller's Crossing
Drawer   2 Folder 12  
Sketches,  April 23, 2003
Drawer   2 Folder 12  
Evaluation Criteria,  April 18, 2003
Drawer   2 Folder 12  
Site Options Study Sketches,  2001
Drawer   2 Folder 12  
Miscellaneous Plans and Drawings
Tube   31  
Area Plan,  undated
Tube   31  
Baxter Road Entrance and Guard Kiosk -- Issued for 100% Final Review,  September 9, 2005
Tube   32  
Building  10/20 Courtyard-Plans Issued for Bidding,  March 30, 2001
Tube   32  
Building 20 -- Stair Tower Addition, Submitted for Administrative Amendment,  February 5, 2004
Tube   32  
Building 28 Loading Dock Renovation and South End Distribution -- Submitted for PUD Site Plan Administrative Amendment,  March 10, 2006
 
Building 35
Tube   33  
Storm Water Infrastructure,  September 16, 2004
Tube   33  
Sitework Bid Package,  October 10, 2005
 
Building 85 -- Fire Pump House and Emergency Services
Tube   34  
Plans Submitted for PUD Site Plan,  April 9, 2003
Tube   34  
Building 85 and Building 75 -- Submitted for PUD Site Plan Construction Approval,  September 25, 2003
Tube   35  
Building 910 Site Demolition and Meadow Restoration -- Issued for Bidding,  March 17, 2008
Tube   35  
Campus Base Maps,  2000
 
Guard Kiosk
Tube   35  
Plans, 5  March 2002
Tube   35  
Plans Issued for Construction,  October 5, 2004
Tube   36  
Huron Parkway Reconstruction Planting Plan,  September 3, 2004
Tube   36  
Huron Parkway Site Improvements -- Issued for Design Development Owner Review,  December 14, 2006
 
Master Plan
Tube   36  
Preliminary Framework Diagrams,  November 2002
Tube   36  
Sketches
Tube   37  
Submitted for PUD,  November 26, 2001
Tube   37  
Traffic Study -- Proposed Changes,  January 15, 2002
Tube   37  
Miscellaneous Plans and Sketches
 
Planting Enhancements
Tube   37  
Issued for Construction,  September 11, 2000
Tube   37  
Phase II,  April 11, 2001
 
Prairie Conversion
Tube   37  
Issued for Bidding,  October 28, 2002
Tube   37  
Sketches,  October 7, 2002
Tube   38  
Southwest Campus Site Restoration -- Check Set,  July 9, 2006
Tube   38  
Miscellaneous Plans and Drawings